The Rough-In Sets the Module: Australian Kitchen Set-Out Before the Order
A flat-pack kitchen is bought as cartons of panels and installed against services that were fixed by other trades, to other standards, before the order was placed. Which dimensions the plumbing, gas and electrical rough-in actually controls, and what a factory can and cannot absorb when the wall is 20 mm out.
29 November 2026 · AU market · Fame Industry Co., Ltd.
The order of trades is the order of the purchase order
A Chinese flat-pack kitchen is a dimensional product built to a drawing, and an Australian kitchen is a service installation built around pipework, gas and cable that arrives before it. When those two sequences are reversed, the cabinet becomes the thing that gets cut on site, and a cut carcass is the one defect a factory cannot inspect out of a shipment. The practical rule is that the rough-in is measured from the finished wall and the floor, recorded as numbers, and signed off before the module list is frozen.
This is not a compliance lecture. It is a cost argument. A six-module run that is set out from a drawing rather than from a site measure will fit a room whose walls are within about 10 mm of square; the same run ordered after a site measure will fit a room that is 30 mm out, because the difference is absorbed by a filler and a scribe strip that cost almost nothing at the factory and cost a day of labour on site. The decision point is the purchase order, not the installation week.
- Finished floor level and finished wall face, not slab and frame, because a 150 mm plinth and a 20 mm tile each move the datum
- Waste centre from the finished wall and from the nearest side wall, in millimetres, for the sink and any second sink
- Hot and cold supply positions and whether they arrive in the wall or through the floor
- Gas bayonet or fixed connection position and its height above finished floor
- Power points, isolation switches and any hard-wired appliance cable, with the appliance schedule attached
AS/NZS 3500: the waste and the two supplies decide the sink base
The AS/NZS 3500 series is the plumbing and drainage standard set an Australian plumber works to, and it is the reason a sink base is not interchangeable with a door base. The sink base has to carry a waste, a trap and two supplies inside a 600 mm wide, 560 mm deep carcass, and it has to leave the trap accessible, because a blocked trap is a service call rather than a rebuild. A factory that has not been told where the waste leaves the wall will build a base with the void in the middle, which is right perhaps half the time.
The cabinet side of this is simple to specify and easy to get wrong. Give the void dimension, give the trap clearance, and give the height of the supply elbows above finished floor. On our sink bases the service void is 90 mm deep across the full width and the back panel is omitted behind the bowl rather than drilled after the fact, because a back panel cut on site loses its edge band and becomes the first place a moisture-resistant carcass fails.
The one line that cannot move is the waste centre. It is set by the bowl, the trap and the fall the plumber needs, and a cabinet cannot negotiate with it: if the waste is 40 mm off the module centre, the base moves or the bowl moves, and moving the base breaks the run.
- Waste centre measured from the finished wall face and from the module centre, both recorded
- Trap type named in the file, because a bottle trap and a P-trap need different clear heights under the bowl
- Supplies in wall or through floor, with elbow height, so the void can be built to suit
- Dishwasher and washing machine connections stated as separate lines, not assumed inside the sink base
AS/NZS 5601: gas is a cabinet constraint, not only a plumber's problem
Gas installations in Australia are governed by AS/NZS 5601, and the parts of it that reach the cabinet are clearance from a burner to a combustible surface, ventilation, and where the connection point is allowed to sit. A melamine-faced panel is a combustible surface, which is why a cooktop base is not a door base with a hole in the top: the panel immediately beside and behind the appliance is a regulated distance from the burner, and that distance has to be built rather than trimmed.
The installer holds the clearance figure and applies it on site. The factory's job is to make the geometry possible: a cooktop base with a 150 mm top drawer rather than a full door, a 60 mm service void so the bayonet stands clear, and no fixed shelf directly under the hob where a connection or an isolation point has to be reached. Where a specification calls for a gas cooktop over a drawer bank, the top drawer depth is the number to agree first, because it sets both the clearance under the appliance and the volume of the carton.
- Cooktop type and cut-out dimensions, gas or induction, before the module list is frozen
- Gas connection position and bayonet height, measured from finished floor
- Whether an isolation point has to be reachable without removing a drawer
- Rangehood model and its published clearance to the cooktop, which is a manufacturer figure applied under AS/NZS 5601
AS/NZS 3000 and the appliance schedule
Electrical installation work is governed by AS/NZS 3000, the Wiring Rules, and the cabinet's relationship to it is mostly about access. An isolation switch behind a cabinet that has to be unscrewed to reach is a defect in the installation, not in the cabinet, but it is the cabinet that gets blamed. The appliance schedule is the document that prevents this: oven, cooktop, dishwasher, rangehood, microwave and any warming drawer, each with its power requirement and whether it is plugged in or hard-wired.
The schedule also decides module widths. A 600 mm oven housing is not a 600 mm base with a hole; it needs its own ventilation path, its own shelf positions and, on a hard-wired appliance, a cable route that does not pass through a drawer box. Getting that list with the order rather than after it is the single cheapest thing an importer can do, because the alternative is a site modification that voids the carcass edge and the lead time at the same time.
- Appliance schedule with model numbers, dimensions and power requirement per appliance
- Oven housing type and whether the appliance vents to the front or the rear
- Dishwasher: built-in, integrated or freestanding, and its service connection side
- Cable route and isolation point position, agreed with the electrician before set-out
Set-out tolerance: what a flat pack can absorb and what it cannot
A flat pack is more forgiving of a bad wall than a rigid cabinet, and less forgiving of a bad datum. Panels are cut to about a millimetre and the cams do the rest, so a carcass will pull square on assembly; what it will not do is bend to a wall that runs 25 mm out over 2,400 mm. That error is absorbed by a filler at the end of the run and a scribe strip at the wall, both of which are cheap at the factory and expensive on site, and both of which have to be ordered rather than improvised.
The other tolerance that gets missed is floor level. Adjustable plinth legs give roughly 20 mm of travel, which covers a slab that is out by the tolerance a tiler would accept; it does not cover a floor that falls 40 mm across a galley. Where the fall is that large, the fix is a levelling batten or a plinth scribe, and the fact that it is needed should be known before the worktop is templated rather than after.
The datum rule follows from both: every site measure is taken from finished floor and finished wall, written down with the date, and attached to the order. A measure taken from slab and frame is a measure of a different room.
- Allow 20 mm filler at each end of a run where the wall is not measured, and name the filler as a line item
- Plinth leg travel is about 20 mm; beyond that, specify a levelling batten rather than longer legs
- Corners: measure both walls and the diagonal, because a 90 degree corner that is 2 degrees out changes the corner unit
- Record the measure with the date and the name of the person who took it, and attach it to the order
The documents that should travel in the carton
The most common delay on an Australian flat-pack installation is not a missing panel, it is a missing drawing. A run of twelve cartons with a hardware bag per module and no module map is a puzzle, and a puzzle on site is billed at site rates. Every run we ship carries a printed module drawing with the cartons numbered to it, the hinge cup positions marked, and the service voids dimensioned; a digital copy goes to the buyer so the install crew can work from a screen if the paper is lost.
The second document is the board certificate. Where an Australian specification names AS/NZS 1859 for reconstituted wood panels, the certificate has to name the class, the board thickness and the test house, and it has to match what actually went into the shipment. A certificate for a different thickness is a different product, and a certificate without a test house is a supplier statement rather than a test result. That file is built from shipping documents, so it has to be requested at the order stage rather than chased after the container lands.
- Module drawing with cartons numbered to modules, hinge positions and service void dimensions
- Hardware bag per module, labelled with the module code rather than the carton number
- Board mill certificate naming class, thickness and test house, for the thickness shipped
- Packing list that separates carcass, fronts, plinth and hardware so a short shipment can be identified before installation starts
What it costs: assembly hours, cartons, and the 40HQ arithmetic
Flat pack is a freight decision that is paid for in labour, and the trade is worth stating in numbers rather than adjectives. On a 2,400 mm galley of four bases and three wall units the assembly is about four and a half hours for one installer with a cordless drill and a hex key, and the run ships as twelve cartons at 0.48 m3 and 92 kg. A rigid equivalent of the same run travels at roughly 0.7 m3 because the cavities cannot be nested, which is about 93 runs in a 40HQ instead of 136.
That difference is the whole argument. The container rate divided by runs per container is the freight line per kitchen, and a 46 percent difference in runs per box moves the landed cost per run more than most buyers expect from a change of format. What it does not change is the site programme: assembly hours are real hours, and on a program where the install crew is the constraint rather than the freight, a rigid carcass can still be the better buy. The point is to make that trade with the arithmetic in front of you, not to pick a format because a competitor did.
- Runs per 40HQ is the number to compare, not price per panel
- Assembly hours per run belong in the site programme, not in a footnote
- A half container is the most expensive freight line in a small program: mix vanities and kitchens in one box rather than shipping twice
- Every carton added to a run comes off the load, so the carton plan is agreed before the first order and changed last
Questions Buyers Ask
Does a flat-pack kitchen need licensed trades in Australia?
Can the cabinets be ordered before the rough-in is complete?
How much wall out-of-square can the run absorb?
What does AS/NZS 1859 mean for an imported melamine carcass?